PGE GIEK S.A.

Function

Main Contractor

Project value

24 000 000 PLN

Installation of tight dampers on the FGD bypass

Scope of works

  • Provision of basic, detailed, and 3D workshop designs.
  • Removal of current flue gas duct dampers
  • Application of chemical-resistant coat on the flue gas ducts
  • Provision of a new thermal insulation
  • Removal of electrical and automation systems related to the power supply and control of dampers along with removal of auxiliary systems (sealing air)
  • Provision of new electrical and automation systems along with all remaining retrofit works that are necessary to start up new dampers (delivery of a new sealing control)
  • All remaining construction and civil works that are required for installation and demolishing works
  • Start-up